团队中的两个成员并肩合作,这两个成员工作能力都很强,但是他们各自的问题解决方法极为不同,导致频繁发生争论和互相不信任。该团队可能处于下列哪个开发阶段?()

A、组建阶段

B、震荡阶段

C、规范阶段

D、成熟阶段

答案
查看答案
相关试题

用象形文字写成的罕见的艺术珍品《东巴厕谱》、《神路图》出自(  )的壁画。

A、白族

B、纳西族

C、傣族

D、彝族

在计划执行中,判断某项工作进度偏差对整个工期的影响,应主要分析()。

A、此项工作的进度偏差与质量的关系

B、此项工作是否位于关键线路上

C、此项工作的进度偏差是否大于总时差

D、此项工作的进度偏差是否大于自由时差

E、此项工作的进度偏差与相应费用的关系

关于顾渚紫笋茶的表述正确的是(  )。

A、产于长兴县

B、唐朝就列为贡品

C、中国十大名茶之一

D、我国产制历史最悠久的名茶

Ravi, like many project (1) , had studied the waterfall model of software development as the primary software life-cycle (2) . He has all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (3) and not as (4) . The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice. To be the most situation, an existing process must be (5) to the new problem. A development process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process. 空白(4)处应选择()

A、parts

B、modules

C、software

D、awhole

在word文档编辑区的任意位置()可选定一个段落

A、单击

B、双击

C、三击

D、右击

最新解答的试题
付款人在进行付款时无()

A.形式审查义务

B.实质审查义务

C.附带审查义务

D.票据外有关事项的审查义务
根据《公司法》的规定,有限责任公司下列人员中,可以提议召开股东会临时会议的是()。
A.总经理B.人数过半数的股东C.监事会主席D.人数为半数的董事
关于股份有限公司中的监事会,下列说法错误的是()

A.监事会负责提议聘请或更换外部审计机构B.监事会主席和副主席由全体监事过半数选举产生C.监事会中的职工代表的比例不得低于三分之一D.监事会应至少每6个月召开一次会议
三北精神的科学内涵
阿里巴巴提供了“企业名称认证”“企业身份认证”不同种类的认证,可以根据自身的